Right now this will be a blog of the trials and tribulations of getting a house built. Also, there may be the occasional ramblings from the goings-on within my head.

Name:
Location: Southwest Wisconsin, United States

Friday, September 23, 2005

Electricity Today, Floor When????

The electricity didn't go quite as planned. The guys who bury the wires did their thing when they said they would. The CongomoPowerCoGuy who actually hooks up the meter was sick that day so he came the next day and installed the meter. Power is now hooked up and working.

I haven't heard yet why the floor hasn't been poured. Quite possibly it is because the rain forecast lately hasn't been condusive to pouring cement.

The infloor heating tubes have been installed by the GeoHeaterCoolerGuy along with the plastic water barrier and insulation.

Now just waiting for trusses to show up and the basement floor to get poured.